Le Baron Condominium Concrete Restoration Schedule REVISED
| Activity | Bldg | Start Date | Complete Date |
| Concrete work Stacks 1 & 2 | East | April 3, 2006 | July 31, 2006 |
| Concrete work Stacks 3 | East | June 22, 2006 | Aug 15, 2006 |
| Concrete work Stacks 4 | East | July 20, 2006 | Aug 30, 2006 |
| Concrete work Stacks 5 | East | July 25, 2006 | Aug 30, 2006 |
| Concrete work Stacks 6 | East | Aug 15, 2006 | Nov 3, 2006 |
| Concrete work Stacks 7 & 8 | East | Oct 15, 2006 | Dec 15, 2006 |
| Concrete work Stacks 10 & 11 | East | Dec 15, 2006 | Feb 15, 2007 |
| Concrete work Stacks 9 | East | Dec 15, 2006 | Feb 15, 2007 |
| Concrete work Stacks 1 & 2 | West | April 3, 2006 | June 15, 2006 |
| Concrete work Stacks 3 & 4 | West | June 15, 2006 | Aug 15, 2006 |
| Concrete work Stacks 5 | West | July 25, 2006 | Aug 30, 2006 |
| Concrete work Stacks 6 | West | Aug 15, 2006 | Sept 20, 2006 |
| Concrete work Stacks 7 & 8 | West | July 31, 2006 | Nov 22, 2006 |